Wednesday, December 7, 2011

12/7/11 - Exterior Siding is complete (Finally)

Well after a year of green zip wall we finally have siding on the house.  Just in time for the snow.  We used a combination of maple plywood and pine ship-lap for the siding.

Just about done.  There is Eli up on the scaffolding, that has to be an OSHA violation.
View from Northwest corner
View from West
View from South

12/7/11 - Drywall finish and painting is done

During the last month and a half Kristin has knocked out a ton of work. First she finished all the drywall, a job that she says we should definitely hire out next time. She also primed and painted all said drywall. Lastly she oiled all the interior plywood. Now all thats left on the interior is floors, electrical finish, bathroom and kitchen build out.